It's been a busy couple of days at my garage-becomes-living-space project. We've had a flurry of activity in preparation for the rough-in inspections. These are the inspections that take place
before the insulation and drywall are installed. At this project, we'll have both a building and electrical inspection.
John Dorn handled the electrical work for me. He installed outlets all the way around the room as well as a outdoor light and outlet at the back door and lights in the two closets. We also relocated the room light in the center of the room and wired it for a ceiling fan. John was great to work with. If you need an electrician, check out his website at
www.JohnDornElectric.com.
I also had Wayne Taylor from
W E S Heating and Cooling add a couple air vents and a return vent so that our room will be heated and cooled.
While they were both working, I was replacing the door into the kitchen and finishing up any framing that needed to be done. Once I had all the structural parts framed for the walls, I had to think about the drywall installation and make sure there were nailers in all the right places to secure drywall. Thinking this through now saves me much frustration later when I'm ready to hang drywall.
I also took the time to attach furring strips all around the room to the block wall that extends up the first 16". For this I used 3/4" plywood because it's less likely to split than a board would be. I attached them using my Ramset gun and 1 1/2" fasteners. This took a slightly less powerful 'load' than what I used to install the fasteners in the solid cement floor.
I'm ready for insulation... just need that inspection first...
-Peter
No comments:
Post a Comment